Answer and Explanation

Your Answer is

Correct Answer is H

Explanation

Each stuffing machine can process 150 envelopes per minute. Each postage machine processes 4 emails per second, which means 240 emails per minute. Because there are 24 stuffing machines in total, it can process 150×4=3600 pieces per minute. You need 3600÷240=15 postage machines